PROINVERSIÓN called for tender the concession of two electrical projects
PROINVERSIÓN, commissioned by the Ministry of Energy and Mines, has structured two new transmission line projects through Self-financed Public-Private Partnership (PPP) modality. The projects will be awarded to the bidder that offers the lowest Total Service Cost for a concession period of 30 years, counted from the date of Commercial Operation Commissioning.
PROINVERSIÓN, commissioned by the Ministry of Energy and Mines, has structured two new transmission line projects through Self-financed Public-Private Partnership (PPP) modality. The projects will be awarded to the bidder that offers the lowest Total Service Cost for a concession period of 30 years, counted from the date of Commercial Operation Commissioning.
Project
“220 kV Reque – Nueva Carhuaquero Link, substation, Lines and Associated expansions”
Estimated investment
US$ 29,8
MILLION (without VAT)
Project
“220/60 kV – 75 MVA Nueva Tumbes SE and 60 kV Nueva Tumbes – Tumbes TL”
Estimated investment
US$ 7,9
MILLION (without VAT)
Project
“220 kV Reque – Nueva Carhuaquero Link, substation, Lines and Associated expansions”
Estimated investment
US$ 29,8
MILLION (without VAT)
Project
“220/60 kV – 75 MVA Nueva Tumbes SE and 60 kV Nueva Tumbes – Tumbes TL”
Estimated investment
US$ 7,9
MILLION (without VAT)
Call for tender:
September 30, 2021
Deadline for submitting qualification request:
1st quarter 2022
Opening of Envelope N ° 2 and Project Award:
2nd quarter 2022
Project “220/60 kV – 75 MVA Nueva Tumbes SE and 60 kV Nueva Tumbes – Tumbes TL”
(only available in Spanish)
Project “220 kV Reque – Nueva Carhuaquero Link, substation, Lines and Associated expansions”
(only available in Spanish)
Renzo Rojas Jiménez
Project Manager in PROINVERSIÓN
rrojas@proinversion.gob.pe