PROINVERSION has called for a Comprehensive Project Contest to grant in concession two new electricity transmission projects
PROINVERSION, commissioned by the Ministry of Energy and Mines, has structured two new electricity transmission projects through a Self-Financed Public-Private Partnership (PPP) modality. The projects will be awarded to the bidder that offers the lowest Total Service Cost for a concession term of 30 years, counted from the Start of Commercial Operation. Both projects will be awarded in a single contest and to a single successful bidder.
With the execution of both projects, the supply of electricity to thousands of families in the northern part of the country will be achieved.
Project
“500 kV Huánuco – Tocache – Celendín – Trujillo link, extensions and associated substations”
Estimated investment
US$ 411.48
millon (Without VAT)
Project
“500 kV Link Celendín – Piura, extensions and associated substations”
Estimated investment
US$ 199.96
millon (Without VAT)
Call for bids:
July 19th and 20th, 2022
Deadline to submit qualification request:
February 2023
Opening of Envelope N° 2 and Award Date:
2nd quarter 2023
Contrat :
“500 kV link Huánuco – Tocache – Celendín – Trujillo, extensions and associated substations”